Difference between revisions of "The 2018 Fall HFE"

From Glen Canyon Dam AMP
Jump to: navigation, search
 
(11 intermediate revisions by the same user not shown)
Line 15: Line 15:
 
== 2018 High Flow Experiment Snapshot ==
 
== 2018 High Flow Experiment Snapshot ==
  
==Sediment Conditions==
+
==Sediment Conditions==  
'''Fall Accounting Period'''
+
'''Fall Accounting Period''' [[File:2018_paria_input.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/station/GCDAMP/09382000#/ '''Paria River gage at Lees Ferry'''] ]]
*Paria input (Jul 1 - Nov 4): 764,255
+
*Paria input (Jul 1 - Nov 4): 753,000
*Accumulated in Upper Marble Canyon (Jul 1 - Oct 1, lower bound) = 195,809
+
*Accumulated in Upper Marble Canyon (Jul 1 - Oct 1, lower bound) = 240,000
*Accumulated in Lower Marble Canyon (Jul 1 - Oct 1, lower bound) = 83,469
+
*Accumulated in Lower Marble Canyon (Jul 1 - Oct 1, lower bound) = -68,000
*Available for HFE:  
+
*Available for HFE: 240,000 + -68,000 = 172,000
 
 
'''HFE Transport'''
+
'''HFE Transport''' [[File:2018 upper marble canyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09380000/09383050 '''Upper Marble Canyon'''] ]]
*Paria input (Nov 5 - 10): 793
+
*Paria input (Nov 5 - 10): 1,119
*Evacuated from Upper Marble Canyon (Nov 5 - 10, lower bound) =  
+
*Evacuated from Upper Marble Canyon (Nov 5 - 10, lower bound) = -360,000
*Evacuated from Lower Marble Canyon (Nov 5 - 10, lower bound) =
+
*Evacuated from Lower Marble Canyon (Nov 5 - 10, lower bound) = -160,000
*Left over in Marble Canyon after HFE (Nov 5 - 10):   
+
*Left over in Marble Canyon after HFE (Nov 5 - 10): 172,000 + 1,119 - 360,000 - 160,000 = -346,881    
 
 
'''Winter Accounting Period'''
+
'''Fall Accounting Period''' [[File:2018 lower marble canyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09383050/09383100 '''Lower Marble Canyon'''] ]]
*Paria input (Nov 11 to Apr 1):  
+
*Paria input (Nov 11 to Apr 1): 366,588
*Evacuated from Upper Marble Canyon (Dec 1 to Apr 1, lower bound) =
+
*Accumulated in Upper Marble Canyon (Dec 1 to Jun 30, lower bound) = -120,000
*Evacuated from Lower Marble Canyon (Dec 1 to Apr 1, lower bound) =
+
*Accumulated in Lower Marble Canyon (Dec 1 to Jun 30, lower bound) = 120,000
*Available for spring HFE:
+
*Available for spring HFE: -120,000 + 120,000 = 0
  
 
==HFE Details==
 
==HFE Details==
Line 41: Line 41:
 
*Nov. 8 - 3:00 p.m. end of High Flow Experiment
 
*Nov. 8 - 3:00 p.m. end of High Flow Experiment
 
*Total duration: 3 days & 10 hours; 2 ½ days at peak release (60 hours)
 
*Total duration: 3 days & 10 hours; 2 ½ days at peak release (60 hours)
*Bypass: 81,000 af
 
  
 
'''Ramp Rates'''
 
'''Ramp Rates'''
Line 48: Line 47:
  
 
'''HFE Release Details'''[[File:2018HFE.jpg|thumb|right|400px|https://www.usbr.gov/uc/rm/gcdHFE/]]  
 
'''HFE Release Details'''[[File:2018HFE.jpg|thumb|right|400px|https://www.usbr.gov/uc/rm/gcdHFE/]]  
*Maximum total release: 38,100 cfs
+
*Maximum total release: '''38,100 cfs'''
 
*Powerplant capacity: 23,100 cfs
 
*Powerplant capacity: 23,100 cfs
 
*River outlet tubes: 15,000 cfs
 
*River outlet tubes: 15,000 cfs
Line 57: Line 56:
 
*Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
 
*Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
 
*Lake elevation is projected to decrease by approximately 7 inches during the 3-day experiment
 
*Lake elevation is projected to decrease by approximately 7 inches during the 3-day experiment
 +
*Estimated acre feet of water bypassed during HFE:  '''81 kaf'''
  
 
'''Costs'''
 
'''Costs'''
*Estimated costs to hydropower: $923,963
+
*Estimated costs to hydropower: '''$923,963'''
*Actual costs to hydropower: TBD
+
*Actual costs to hydropower: [[Media:HFE 2019 Report V3 tv qp.docx| '''$1,300,000''']]
 
*Direct expenses for removal of concession assets: TBD
 
*Direct expenses for removal of concession assets: TBD
  
 
== SUPPORTING DOCUMENTS ==  
 
== SUPPORTING DOCUMENTS ==  
 +
*[[Media:HFE 2019 Report V3 tv qp.docx| Financial Analysis of Experimental Releases Conducted at Glen Canyon Dam during Water Year 2019 ]]
 
*[https://www.usbr.gov/uc/progact/amp/twg/2018-10-10-twg-meeting/Attach_07.pdf Possible LTEMP Experiment: Fall 2018 HFE PPT]
 
*[https://www.usbr.gov/uc/progact/amp/twg/2018-10-10-twg-meeting/Attach_07.pdf Possible LTEMP Experiment: Fall 2018 HFE PPT]
 
*[https://www.usbr.gov/uc/rm/gcdHFE/pdfs/20181018%20DOI%20HFE%20Decision%20Memo_ASWS%20Signed_with%20attachments.pdf 2018 High Flow Experimental Release Decision Memorandum]
 
*[https://www.usbr.gov/uc/rm/gcdHFE/pdfs/20181018%20DOI%20HFE%20Decision%20Memo_ASWS%20Signed_with%20attachments.pdf 2018 High Flow Experimental Release Decision Memorandum]

Latest revision as of 15:58, 3 November 2022

High Flow Experiment- 2018
2018HFE lights.jpg

2018 High Flow Experiment Snapshot

Sediment Conditions

Fall Accounting Period
  • Paria input (Jul 1 - Nov 4): 753,000
  • Accumulated in Upper Marble Canyon (Jul 1 - Oct 1, lower bound) = 240,000
  • Accumulated in Lower Marble Canyon (Jul 1 - Oct 1, lower bound) = -68,000
  • Available for HFE: 240,000 + -68,000 = 172,000
HFE Transport
  • Paria input (Nov 5 - 10): 1,119
  • Evacuated from Upper Marble Canyon (Nov 5 - 10, lower bound) = -360,000
  • Evacuated from Lower Marble Canyon (Nov 5 - 10, lower bound) = -160,000
  • Left over in Marble Canyon after HFE (Nov 5 - 10): 172,000 + 1,119 - 360,000 - 160,000 = -346,881
Fall Accounting Period
  • Paria input (Nov 11 to Apr 1): 366,588
  • Accumulated in Upper Marble Canyon (Dec 1 to Jun 30, lower bound) = -120,000
  • Accumulated in Lower Marble Canyon (Dec 1 to Jun 30, lower bound) = 120,000
  • Available for spring HFE: -120,000 + 120,000 = 0

HFE Details

Schedule & Duration

  • Nov. 5 - 6:00 a.m. begin upramp to powerplant capacity (~23,100 cfs) [7 generation units]
  • Nov. 5 - 11:00 a.m. open bypass tubes, reach full bypass at 2:00 p.m. (38,100 cfs)
  • Nov. 8 - 9:00 a.m. end of bypass
  • Nov. 8 - 3:00 p.m. end of High Flow Experiment
  • Total duration: 3 days & 10 hours; 2 ½ days at peak release (60 hours)

Ramp Rates

  • Ramp up: 4,000 cfs/hr from 6,500 - 23,100 cfs, then 3,750 cfs/hr to peak (38,100 cfs)
  • Ramp down: 1,875 cfs/hr from 38,100 – 23,100 cfs, then 2,500 cfs/hr to 9,000 cfs
HFE Release Details
  • Maximum total release: 38,100 cfs
  • Powerplant capacity: 23,100 cfs
  • River outlet tubes: 15,000 cfs
  • Hydropower generation units available: 7 (one unit off-line for replacement)
  • River outlet tubes: 4

Releases and Lake Elevation

  • Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
  • Lake elevation is projected to decrease by approximately 7 inches during the 3-day experiment
  • Estimated acre feet of water bypassed during HFE: 81 kaf

Costs

  • Estimated costs to hydropower: $923,963
  • Actual costs to hydropower: $1,300,000
  • Direct expenses for removal of concession assets: TBD