Difference between revisions of "GCDAMP- HFE 2014"

From Glen Canyon Dam AMP
Jump to: navigation, search
Line 30: Line 30:
  
 
== SUPPORTING DOCUMENTS ==
 
== SUPPORTING DOCUMENTS ==
*[[Media:131025 Final HFE Memo to Larry Walkoviak 10-25-13 with attachment.PDF |131025 Final HFE Memo to Larry Walkoviak 10-25-13 with attachment]]
+
 
*[[Media:131022 Basin States Knowles.pdf |131022 Fall 2013 HFE Protocol Decision Process]]
+
*[[Media:131022 HFE Routing - start11th9AM.pdf |131022 2013 HFE Locations and dates of hydrograph routing]]
+
*[[Media:131022 Basin States Schmidt.pdf |131022 System Overview to Basin States- USGS Schmidt]]
+
*[[Media:131022 Basin States Vanderkooi.pdf |131022 USGS Science Overview- Fisheries and Aquatic Ecology to Basin States- SVanderkooi]]
+
  
 
== COMPLIANCE ==
 
== COMPLIANCE ==

Revision as of 11:18, 12 July 2016

SUMMARY

High Flow Experiment- 2014
CRC 121119 0038.JPG
  • HFE DETAILS -SUMMARY:
  • Sediment in the system: 1.195 Million metric tons
  • Peak CFS: ~37,500
  • Estimated costs to WAPA Hydropower: $1.749 million
  • Estimated acre feet of water bypassed during HFE: approx. 129,000 af
  • Hourly Releases before and after HFE: fluctuate between 5,000 to 8,000 cfs
  • Direct expenses for removal of concession assets: $9,961
  • Units available: 7
  • Powerplant capacity = ~19,100 cfs
  • November volume = 670 kaf
  • Start Upramp: November 10th at 9:00am
  • Finish HFE: November 15, 2pm
  • Total HFE duration: 5 days, 3 hrs November 10-15
  • HFE 2014 represents the 3rd controlled high flow release conducted under the HFE Protocol.

SUPPORTING DOCUMENTS

COMPLIANCE

  • A 30-day letter was sent notifying MOA signatories of a possible HFE in October 9, 2014.
  • DOI consultation meeting with the Basin States_ October 07, 2014.
  • Government to Government tribal consultation: Pueblo of Zuni_
  • Government to Government tribal consultation: Navajo Nation_
  • Report made available and presented at AMWG_ August 27-28, 2014.
  • USBR conducted a webinar with TWG, October 1th, 2014.

CONCERNS

  • Pueblo of Zuni: concern that multiple HFE's under the HFE protocol could result in power cost increases for individual rate payers.

Request to USBR made for detailed description on how the economic effects of multiple HFEs on power rate payers will be monitored.

SEDIMENT

  • "The quantity of sand available for this HFE is huge, and to put it in perspective, there will be more sand AFTER this HFE (about 800,000 mt) than before last year's HFE (about 650,000 mt)." [GKnowles_TWG MM_131106]

ADDITIONAL




  • SVaderkooi Fact Check on swimming pool comparison: Wikipedia Swimming pool size. Assuming a depth of 2 m, a 50 m x 25 m pool equals about 88,000 cubic feet. At peak Reclamation said the release from the dam was around 34,000 cfs so an olympic-sized pool would fill in about 2.6 s. Note that the USGS gage at Lees Ferry measured peak flow at about 37,000 cfs, so a little quicker (about 2.4 s) if you use that number.

Contributor: Category: Sediment, Recreation, Water delivery