A 2021 Spring HFE
From Glen Canyon Dam AMP
Revision as of 15:45, 20 October 2021 by Cellsworth (Talk | contribs)
High Flow Experiment- 2021 | |
Contents
2021 Spring High Flow Experiment Snapshot
- A 2021 Spring HFE was not conducted for lack of adequate sediment input from the Paria River
Sediment Conditions
Spring Accounting Period
- Paria input (Dec 1 to Jun 30): 10,602 mt
- Evacuated from Upper Marble Canyon (Dec 1 to Jun 30, lower bound) = -93,000 mt
- Evacuated from Lower Marble Canyon (Dec 1 to Jun 30, lower bound) = +10,000 mt
- Available for Spring HFE: -83,000 mt
SUPPORTING DOCUMENTS
COMPLIANCE
CONCERNS
ADDITIONAL