GCDAMP- HFE 2013

From Glen Canyon Dam AMP
Revision as of 15:59, 28 October 2013 by Jthiriot (Talk | contribs) (zuni)

Jump to: navigation, search
High Flow Experiment- 2013
CRC 121119 0038.JPG
  • HFE DETAILS -SUMMARY:
  • Sediment in the system: 1.5 Million metric tons
  • Starts on Monday, November 11th and ends November 16th
  • Estimated costs to WAPA Hydropower: $1.74 million
  • Estimated acre feet of water bypassed during HFE: approx. 129,000 af
  • Hourly Releases before and after HFE: fluctuate between 5,000 to 8,000 cfs

SUPPORTING DOCUMENTS

COMPLIANCE

  • A 30-day letter was sent notifying MOA signatories of a possible HFE in November 2013.
  • DOI consultation meeting with the Basin States_ October 22, 2013.
  • Government to Government tribal consultation: Pueblo of Zuni_ September 10, 2013.
  • Government to Government tribal consultation: Navajo Nation_ September 11, 2013.

CONCERNS

  • Pueblo of Zuni: concern that multiple HFE's under the HFE protocol could result in power cost increases for individual rate payers.

Request to USBR made for detailed description on how the economic effects of multiple HFEs on power rate payers will be monitored.

TBD





Contributor: Category: Sediment, Recreation, Water delivery