The 2018 Fall HFE

From Glen Canyon Dam AMP
Revision as of 14:36, 2 July 2020 by Cellsworth (Talk | contribs)

Jump to: navigation, search
High Flow Experiment- 2018
2018HFE lights.jpg

2018 High Flow Experiment Snapshot

Sediment Conditions

Fall Accounting Period
  • Paria input (Jul 1 - Nov 4): 753,000
  • Accumulated in Upper Marble Canyon (Jul 1 - Oct 1, lower bound) = 240,000
  • Accumulated in Lower Marble Canyon (Jul 1 - Oct 1, lower bound) = -68,000
  • Available for HFE: 240,000 + -68,000 = 172,000
HFE Transport
  • Paria input (Nov 5 - 10): 1,119
  • Evacuated from Upper Marble Canyon (Nov 5 - 10, lower bound) = -360,000
  • Evacuated from Lower Marble Canyon (Nov 5 - 10, lower bound) = -160,000
  • Left over in Marble Canyon after HFE (Nov 5 - 10): 172,000 + 1,119 - 360,000 - 160,000 = -346,881
Winter Accounting Period
  • Paria input (Nov 11 to Apr 1): 366,588
  • Accumulated in Upper Marble Canyon (Dec 1 to Jun 30, lower bound) = -120,000
  • Accumulated in Lower Marble Canyon (Dec 1 to Jun 30, lower bound) = 120,000
  • Available for spring HFE: -120,000 + 120,000 = 0

HFE Details

Schedule & Duration

  • Nov. 5 - 6:00 a.m. begin upramp to powerplant capacity (~23,100 cfs) [7 generation units]
  • Nov. 5 - 11:00 a.m. open bypass tubes, reach full bypass at 2:00 p.m. (38,100 cfs)
  • Nov. 8 - 9:00 a.m. end of bypass
  • Nov. 8 - 3:00 p.m. end of High Flow Experiment
  • Total duration: 3 days & 10 hours; 2 ½ days at peak release (60 hours)

Ramp Rates

  • Ramp up: 4,000 cfs/hr from 6,500 - 23,100 cfs, then 3,750 cfs/hr to peak (38,100 cfs)
  • Ramp down: 1,875 cfs/hr from 38,100 – 23,100 cfs, then 2,500 cfs/hr to 9,000 cfs
HFE Release Details
  • Maximum total release: 38,100 cfs
  • Powerplant capacity: 23,100 cfs
  • River outlet tubes: 15,000 cfs
  • Hydropower generation units available: 7 (one unit off-line for replacement)
  • River outlet tubes: 4

Releases and Lake Elevation

  • Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
  • Lake elevation is projected to decrease by approximately 7 inches during the 3-day experiment
  • Estimated acre feet of water bypassed during HFE: 81 kaf

Costs

  • Estimated costs to hydropower: $923,963
  • Actual costs to hydropower: $1,300,000
  • Direct expenses for removal of concession assets: TBD