*Sediment in the system:  '''TBD'''
+
*Sediment in the system:  '''962,000 metric tons'''
 
*Peak CFS:  '''35,100 cfs'''  
 
*Peak CFS:  '''35,100 cfs'''  
 
*Powerplant capacity = '''20,100 cfs'''  
 
*Powerplant capacity = '''20,100 cfs'''  
Line 26: Line 26:
 
*Actual costs to hydropower:  '''TBD'''
 
*Actual costs to hydropower:  '''TBD'''
 
*Direct expenses for removal of concession assets:  '''TBD'''
 
*Direct expenses for removal of concession assets:  '''TBD'''
*Start Upramp: '''TBD'''  
+
*Start Upramp: '''Nov 7, 2016'''  
*Finish HFE: '''TBD'''   
+
*Finish HFE: '''Nov 11, 2016'''   
 
*Total HFE duration:  '''96 hrs'''  
 
*Total HFE duration:  '''96 hrs'''  
 
*HFE 2016 represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
 
*HFE 2016 represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].

Revision as of 12:07, 19 October 2016

SUMMARY

High Flow Experiment- 2016
CRC 121119 0038.JPG
  • Sediment in the system: 962,000 metric tons
  • Peak CFS: 35,100 cfs
  • Powerplant capacity = 20,100 cfs
  • Units available: 6
  • Bypass tube capacity = 15,000 cfs
  • Estimated acre feet of water bypassed during HFE: 125 kaf
  • November volume = 745 kaf
  • Hourly Releases before and after HFE: fluctuate between 6,000 to 9,000 cfs
  • Estimated costs to hydropower: $1.4 million
  • Actual costs to hydropower: TBD
  • Direct expenses for removal of concession assets: TBD
  • Start Upramp: Nov 7, 2016
  • Finish HFE: Nov 11, 2016
  • Total HFE duration: 96 hrs
  • HFE 2016 represents the 4th controlled high flow release conducted under the HFE Protocol.