Difference between revisions of "GCDAMP- HFE 2016"

From Glen Canyon Dam AMP
Jump to: navigation, search
Line 14: Line 14:
  
 
== 2016 High Flow Experiment Snapshot ==
 
== 2016 High Flow Experiment Snapshot ==
*HFE 2016 represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
+
*The 2016 HFE represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
  
 
'''Schedule & Duration'''
 
'''Schedule & Duration'''

Revision as of 14:20, 14 November 2016

High Flow Experiment- 2016
CRC 121119 0038.JPG

2016 High Flow Experiment Snapshot

  • The 2016 HFE represents the 4th controlled high flow release conducted under the HFE Protocol.

Schedule & Duration

  • Nov. 7 - 6 a.m. begin upramp to powerplant capacity ( ~21,000 cfs)
  • Nov. 7 - 10:00 a.m. open bypass tubes, reach full bypass at 12:00 p.m.
  • Nov. 11 - 12:00 p.m. end of bypass
  • Nov. 12 - 3:00 a.m. end of HFE
  • Total duration: 5 days & 5 hours (96 hours at peak release)

Ramp Rates

  • Ramp up: 4,000 cfs/hr from 6,500 - 21,000 cfs, then 3,750 cfs/hr to peak (36,000 cfs)
  • Ramp down: 1,875 cfs/hr from 36,000 - 21,000 cfs, then 1,500 cfs/hr to 9,000 cfs

HFE Release Details

  • Maximum total release: 36,000 cfs
  • Powerplant capacity: 21,000 cfs
  • River outlet tubes: 15,000 cfs
  • Hydropower generation units available: 6
  • River outlet tubes: 4

Releases and Lake Elevation

  • Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
  • Lake elevation is projected to decrease by approximately 2.5 feet during the 5-day period
  • Estimated acre feet of water bypassed during HFE: 125 kaf
  • November volume = 745 kaf

Costs

  • Estimated costs to hydropower: $1.4 million
  • Actual costs to hydropower: TBD
  • Direct expenses for removal of concession assets: TBD

SUPPORTING DOCUMENTS

COMPLIANCE

CONCERNS

SEDIMENT

  • Sediment in the system: 962,000 metric tons

ADDITIONAL