GCDAMP- HFE 2016

From Glen Canyon Dam AMP
Revision as of 15:18, 18 October 2016 by Cellsworth (Talk | contribs)

Jump to: navigation, search

SUMMARY

High Flow Experiment- 2016
CRC 121119 0038.JPG
  • Sediment in the system: TBD
  • Peak CFS: 35,100 cfs
  • Powerplant capacity = 20,100 cfs
  • Units available: 6
  • Bypass tube capacity = 15,000 cfs
  • Estimated acre feet of water bypassed during HFE: 125 kaf
  • November volume = 745 kaf
  • Hourly Releases before and after HFE: fluctuate between 6,000 to 9,000 cfs
  • Estimated costs to hydropower: $1.4 million
  • Actual costs to hydropower: TBD
  • Direct expenses for removal of concession assets: TBD
  • Start Upramp: TBD
  • Finish HFE: TBD
  • Total HFE duration: 96 hrs
  • HFE 2016 represents the 4th controlled high flow release conducted under the HFE Protocol.

SUPPORTING DOCUMENTS

COMPLIANCE

CONCERNS

SEDIMENT

ADDITIONAL