*'''HFE DETAILS -SUMMARY:'''  
+
 
*Sediment in the system: '''1,195,000 metric tons'''
+
 
*Peak CFS: '''~37,500'''  
+
== 2014 High Flow Experiment Snapshot ==
*Estimated costs to hydropower: '''$1.749 million'''
+
*The 2014 HFE represents the '''3rd''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
*Actual costs to hydropower: '''$2.1 million'''
+
A preliminary analysis of these images indicates that sandbar size increased at 57% of sites, remained unchanged and 31% of sites, and decreased at 12% of sites, a response similar to those observed during each of the 2012-2013 HFEs.
*Estimated acre feet of water bypassed during HFE: '''approx. 129,000 af'''
+
*Before and after images from the November 2014 HFE from each of the 45 sandbar sites monitored with remotely deployed digital cameras are available [https://grandcanyon.usgs.gov/gisapps/sandbartour2014/index.html? '''here'''].
*Hourly Releases before and after HFE:  fluctuate between '''5,000 to 8,000 cfs'''
+
 
*Direct expenses for removal of concession assets: '''$9,961'''
+
==Sediment Conditions==
*Units available: '''7'''  
+
'''Fall Accounting Period''' [[File:2014 FallHFE Paria.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/station/GCDAMP/09382000#/ '''Paria River gage at Lees Ferry'''] ]]
*Powerplant capacity = '''~19,100 cfs'''  
+
*Paria input (Jul 1 - Nov 9): 1,213,000
 +
*Accumulated in Upper Marble Canyon (Jul 1 - Nov 9, lower bound) = 815,000
 +
*Accumulated in Lower Marble Canyon (Jul 1 - Nov 9, lower bound) = 239,000
 +
*Available for HFE: 815,000 + 239,000 = 1,054,000
 +
 +
'''HFE Transport''' [[File:2014 FallHFE UpperMarbleCanyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09380000/09383050 '''Upper Marble Canyon'''] ]]
 +
*Paria input (Nov 10 - 15): 0
 +
*Evacuated from Upper Marble Canyon (Nov 10 - 15, lower bound) = -631,000
 +
*Evacuated from Lower Marble Canyon (Nov 10 - 15, lower bound) = -37,000
 +
*Left over in Marble Canyon after HFE (Nov 10 - 15): 1,054,000 - 631,000 - 37,000 = 386,000
 +
 +
'''Spring Accounting Period''' [[File:2014 FallHFE LowerMarbleCanyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09383050/09383100 '''Lower Marble Canyon'''] ]]
 +
*Paria input (Dec 1 to Apr 1): 13,000
 +
*Evacuated from Upper Marble Canyon (Dec 1 to Apr 1, lower bound) = -229,000
 +
*Accumulated in Lower Marble Canyon (Dec 1 to Apr 1, lower bound) = 83,000
 +
*Available for spring HFE: -229,000 + 83,000 = -146,000 
 +
 
 +
==HFE Details==
 +
'''Schedule & Duration'''
 +
*November 10, 9:00 am begin upramp to powerplant capacity (~9,100 cfs)
 +
*November 15, 2:00 pm end of HFE
 +
*Total duration: 5 days & 5 hours ('''96 hours''' at peak release)
 +
 
 +
'''Ramp Rates'''
 +
*Ramp up: 4,000 cfs/hr from 5,000 - 19,100 cfs, then 3,750 cfs/hr to peak (37,500 cfs)
 +
*Ramp down: 1,875 cfs/hr from 37,500 - 19,100 cfs, then 1,500 cfs/hr to 8,000 cfs
 +
 
 +
'''HFE Release Details'''
 +
*Maximum total release: '''~37,500 cfs'''
 +
*Powerplant capacity: ~19,100 cfs
 +
*River outlet tubes: 15,000 cfs
 +
*Hydropower generation units available: 7
 +
*River outlet tubes: 4
 +
 
 +
'''Releases and Lake Elevation'''
 +
*Releases will range from 6,500 to 9,000 cfs prior to and after the HFE
 +
*Estimated acre feet of water bypassed during HFE:  '''~129 kaf'''
 
*November volume = '''670 kaf'''
 
*November volume = '''670 kaf'''
*Start Upramp: '''November 10, 9:00 am '''
+
 
*Finish HFE: '''November 15, 2:00 pm '''
+
'''Costs'''
*Total HFE duration:  '''96 hrs'''  
+
*Estimated costs to hydropower: '''$1.749 million '''
*HFE 2014 represents the '''3rd''' controlled high flow release conducted under the HFE Protocol.
+
*Actual costs to hydropower[[Media:Financial Analysis of Experimental Releases Conducted at Glen Canyon Dam WY15.pdf| '''$2.1 million''']]
 +
*Direct expenses for removal of concession assets:  '''$9,961'''
  
 
== SUPPORTING DOCUMENTS ==
 
== SUPPORTING DOCUMENTS ==
 +
*[[Media:Financial Analysis of Experimental Releases Conducted at Glen Canyon Dam WY15.pdf| Financial Analysis of Experimental Releases Conducted at Glen Canyon Dam during Water Year 2015 by D.J. Graziano, L.A. Poch, and T.D. Veselka.]]
 
*[https://drive.google.com/file/d/0BwY-Z2c3NTUGQURtV2s3eWJqRHM/view Updates on 2014 HFE, 2015 Paria sediment inputs, and sediment mass balance]
 
*[https://drive.google.com/file/d/0BwY-Z2c3NTUGQURtV2s3eWJqRHM/view Updates on 2014 HFE, 2015 Paria sediment inputs, and sediment mass balance]
 
*[http://www.usbr.gov/uc/rm/amp/amwg/mtgs/14aug27/HFE_Memo_14oct24_PPT.pdf| Memo from Jennifer Gimbel, Chair, Glen Canyon Leadership Team dated October 24, 2014, to Brent Rhees, Acting Regional Director, Subject: Approval of Recommendation for Experimental High-Flow Release from Glen Canyon Dam, November 2014]*[http://www.usbr.gov/uc/rm/amp/twg/mtgs/14oct28/Attach_02.pdf Fall 2014 HFE Planning and PPT]
 
*[http://www.usbr.gov/uc/rm/amp/amwg/mtgs/14aug27/HFE_Memo_14oct24_PPT.pdf| Memo from Jennifer Gimbel, Chair, Glen Canyon Leadership Team dated October 24, 2014, to Brent Rhees, Acting Regional Director, Subject: Approval of Recommendation for Experimental High-Flow Release from Glen Canyon Dam, November 2014]*[http://www.usbr.gov/uc/rm/amp/twg/mtgs/14oct28/Attach_02.pdf Fall 2014 HFE Planning and PPT]
Line 48: Line 85:
 
*'''Pueblo of Zuni:''' concern that multiple HFE's under the HFE protocol could result in power cost increases for individual rate payers.
 
*'''Pueblo of Zuni:''' concern that multiple HFE's under the HFE protocol could result in power cost increases for individual rate payers.
 
''Request to USBR made for detailed description on how the economic effects of multiple HFEs on power rate payers will be monitored.''
 
''Request to USBR made for detailed description on how the economic effects of multiple HFEs on power rate payers will be monitored.''
 
== SEDIMENT ==
 
* "The quantity of sand available for this HFE is huge, and to put it in perspective, there will be more sand AFTER this HFE (about 800,000 mt) than before last year's HFE (about 650,000 mt)." [GKnowles_TWG MM_131106]
 
[[File:2014 Paria inputs.jpg|400px]] <br> 2014 Paria River discharge and cumulative sand inputs
 
  
 
== ADDITIONAL ==
 
== ADDITIONAL ==
Line 58: Line 91:
 
*Glen Canyon Dam will start pumping an '''Olympic-sized swimming pool worth of water''' into the Colorado River '''every other minute--INCORRECT'''--[http://azdailysun.com/news/local/high-flow-releases-from-glen-canyon-dam-set-next-week/article_41c350e2-45c5-11e3-b854-0019bb2963f4.html LINK]
 
*Glen Canyon Dam will start pumping an '''Olympic-sized swimming pool worth of water''' into the Colorado River '''every other minute--INCORRECT'''--[http://azdailysun.com/news/local/high-flow-releases-from-glen-canyon-dam-set-next-week/article_41c350e2-45c5-11e3-b854-0019bb2963f4.html LINK]
 
*[http://www.waterworld.com/articles/2013/11/sediment-deposits-following-rainstorms-utilized-by-science-based-plan.html “By sending enough water downstream '''to fill an Olympic-sized swimming pool every few seconds...''']  
 
*[http://www.waterworld.com/articles/2013/11/sediment-deposits-following-rainstorms-utilized-by-science-based-plan.html “By sending enough water downstream '''to fill an Olympic-sized swimming pool every few seconds...''']  
*[http://www.waterworld.com/articles/2013/11/sediment-deposits-following-rainstorms-utilized-by-science-based-plan.html the 96-hour-release will pick up enough sand from river channels '''to fill a building as big as a football field and as tall as the Washington Monument, all the way to the brim.” ''']  
+
*[http://www.waterworld.com/articles/2013/11/sediment-deposits-following-rainstorms-utilized-by-science-based-plan.html The 96-hour-release will pick up enough sand from river channels '''to fill a building as big as a football field and as tall as the Washington Monument, all the way to the brim.” ''']  
 
*Lake Powell is expected to drop '''2.5 feet''' during the course of the week. --[http://azdailysun.com/news/local/high-flow-releases-from-glen-canyon-dam-set-next-week/article_41c350e2-45c5-11e3-b854-0019bb2963f4.html LINK]
 
*Lake Powell is expected to drop '''2.5 feet''' during the course of the week. --[http://azdailysun.com/news/local/high-flow-releases-from-glen-canyon-dam-set-next-week/article_41c350e2-45c5-11e3-b854-0019bb2963f4.html LINK]
 
----
 
----

Latest revision as of 15:40, 2 July 2020


High Flow Experiment- 2014
CRC 121119 0038.JPG


2014 High Flow Experiment Snapshot

  • The 2014 HFE represents the 3rd controlled high flow release conducted under the HFE Protocol.

A preliminary analysis of these images indicates that sandbar size increased at 57% of sites, remained unchanged and 31% of sites, and decreased at 12% of sites, a response similar to those observed during each of the 2012-2013 HFEs.

  • Before and after images from the November 2014 HFE from each of the 45 sandbar sites monitored with remotely deployed digital cameras are available here.

Sediment Conditions

Fall Accounting Period
  • Paria input (Jul 1 - Nov 9): 1,213,000
  • Accumulated in Upper Marble Canyon (Jul 1 - Nov 9, lower bound) = 815,000
  • Accumulated in Lower Marble Canyon (Jul 1 - Nov 9, lower bound) = 239,000
  • Available for HFE: 815,000 + 239,000 = 1,054,000
HFE Transport
  • Paria input (Nov 10 - 15): 0
  • Evacuated from Upper Marble Canyon (Nov 10 - 15, lower bound) = -631,000
  • Evacuated from Lower Marble Canyon (Nov 10 - 15, lower bound) = -37,000
  • Left over in Marble Canyon after HFE (Nov 10 - 15): 1,054,000 - 631,000 - 37,000 = 386,000
Spring Accounting Period
  • Paria input (Dec 1 to Apr 1): 13,000
  • Evacuated from Upper Marble Canyon (Dec 1 to Apr 1, lower bound) = -229,000
  • Accumulated in Lower Marble Canyon (Dec 1 to Apr 1, lower bound) = 83,000
  • Available for spring HFE: -229,000 + 83,000 = -146,000

HFE Details

Schedule & Duration

  • November 10, 9:00 am begin upramp to powerplant capacity (~9,100 cfs)
  • November 15, 2:00 pm end of HFE
  • Total duration: 5 days & 5 hours (96 hours at peak release)

Ramp Rates

  • Ramp up: 4,000 cfs/hr from 5,000 - 19,100 cfs, then 3,750 cfs/hr to peak (37,500 cfs)
  • Ramp down: 1,875 cfs/hr from 37,500 - 19,100 cfs, then 1,500 cfs/hr to 8,000 cfs

HFE Release Details

  • Maximum total release: ~37,500 cfs
  • Powerplant capacity: ~19,100 cfs
  • River outlet tubes: 15,000 cfs
  • Hydropower generation units available: 7
  • River outlet tubes: 4

Releases and Lake Elevation

  • Releases will range from 6,500 to 9,000 cfs prior to and after the HFE
  • Estimated acre feet of water bypassed during HFE: ~129 kaf
  • November volume = 670 kaf

Costs

  • Estimated costs to hydropower: $1.749 million
  • Actual costs to hydropower: $2.1 million
  • Direct expenses for removal of concession assets: $9,961

SUPPORTING DOCUMENTS

COMPLIANCE

  • A 30-day letter was sent notifying MOA signatories of a possible HFE in October 9, 2014.
  • DOI consultation meeting with the Basin States_ October 07, 2014.
  • Government to Government tribal consultation: Pueblo of Zuni_
  • Government to Government tribal consultation: Navajo Nation_
  • Report made available and presented at AMWG_ August 27-28, 2014.
  • USBR conducted a webinar with TWG, October 1th, 2014.

CONCERNS

  • Pueblo of Zuni: concern that multiple HFE's under the HFE protocol could result in power cost increases for individual rate payers.

Request to USBR made for detailed description on how the economic effects of multiple HFEs on power rate payers will be monitored.

ADDITIONAL




  • SVaderkooi Fact Check on swimming pool comparison: Wikipedia Swimming pool size. Assuming a depth of 2 m, a 50 m x 25 m pool equals about 88,000 cubic feet. At peak Reclamation said the release from the dam was around 34,000 cfs so an olympic-sized pool would fill in about 2.6 s. Note that the USGS gage at Lees Ferry measured peak flow at about 37,000 cfs, so a little quicker (about 2.4 s) if you use that number.

Contributor: Category: Sediment, Recreation, Water delivery