== 2016 High Flow Experiment Snapshot ==
 
== 2016 High Flow Experiment Snapshot ==
 +
*The 2016 HFE represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
 +
*A preliminary analysis of these images indicates that sandbar size increased at 55% of sites, remained unchanged and 30% of sites, and decreased at 15% of sites, a response similar to those observed during each of the 2012-2014 HFEs.
 +
*Before and after images from the November 2016 HFE from each of the 45 sandbar sites monitored with remotely deployed digital cameras are available [https://grandcanyon.usgs.gov/gisapps/sandbartour2016/index.html? '''here'''].
  
*HFE 2016 represents the '''4th''' controlled high flow release conducted under the [http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol].
+
==Sediment Conditions==
*Sediment in the system: '''962,000 metric tons'''
+
'''Fall Accounting Period''' [[File:2016 FallHFE Paria.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/station/GCDAMP/09382000#/ '''Paria River gage at Lees Ferry'''] ]]  
 +
*Paria input (Jul 1 - Nov 6): 844,748
 +
*Accumulated in Upper Marble Canyon (Jul 1 - Nov 6, lower bound) = 373,000
 +
*Accumulated in Lower Marble Canyon (Jul 1 - Nov 6, lower bound) = 72,000
 +
*Available for HFE: 373,000 + 72,000 = 445,000
 +
 +
'''HFE Transport''' [[File:2016 FallHFE UpperMarbleCanyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09380000/09383050 '''Upper Marble Canyon'''] ]]
 +
*Paria input (Nov 7 - 12): 1,000
 +
*Evacuated from Upper Marble Canyon (Nov 7 - 12, lower bound) = -492,000
 +
*Evacuated from Lower Marble Canyon (Nov 7 - 12, lower bound) = -184,000
 +
*Left over in Marble Canyon after HFE (Nov 7 - 12): 445,000 + 1,000 - 492,000 - 184,000 = -230,000
 +
 +
'''Spring Accounting Period''' [[File:2016 FallHFE LowerMarbleCanyon.png|thumb|right|400px|[http://www.gcmrc.gov/discharge_qw_sediment/reach/GCDAMP/09383050/09383100 '''Lower Marble Canyon'''] ]]
 +
*Paria input (Dec 1 to Apr 1): 160,000
 +
*Evacuated from Upper Marble Canyon (Dec 1 to Apr 1, lower bound) = -241,000
 +
*Evacuated from Lower Marble Canyon (Dec 1 to Apr 1, lower bound) = -81,000
 +
*Available for spring HFE: -241,000 - 81,000 = -322,000 
  
 +
==HFE Details==
 
'''Schedule & Duration'''
 
'''Schedule & Duration'''
 
*Nov. 7 - 6 a.m. begin upramp to powerplant capacity ( ~21,000 cfs)  
 
*Nov. 7 - 6 a.m. begin upramp to powerplant capacity ( ~21,000 cfs)  
Line 23: Line 43:
 
*Nov. 11 - 12:00 p.m. end of bypass
 
*Nov. 11 - 12:00 p.m. end of bypass
 
*Nov. 12 - 3:00 a.m. end of HFE
 
*Nov. 12 - 3:00 a.m. end of HFE
*Total duration: 5 days & 5 hours; '''96 hours''' at peak release
+
*Total duration: 5 days & 5 hours ('''96 hours''' at peak release)
  
 
'''Ramp Rates'''
 
'''Ramp Rates'''
Line 44: Line 64:
 
'''Costs'''
 
'''Costs'''
 
*Estimated costs to hydropower:  '''$1.4 million'''
 
*Estimated costs to hydropower:  '''$1.4 million'''
*Actual costs to hydropower:  '''TBD'''
+
*Actual costs to hydropower:  [https://publications.anl.gov/anlpubs/2019/06/151713.pdf '''1.15 million''']
 
*Direct expenses for removal of concession assets:  '''TBD'''
 
*Direct expenses for removal of concession assets:  '''TBD'''
  
 
== SUPPORTING DOCUMENTS ==
 
== SUPPORTING DOCUMENTS ==
 +
*[https://publications.anl.gov/anlpubs/2019/06/151713.pdf Financial Analysis of Experimental Releases Conducted at Glen Canyon Dam during Water Year 2017]
 
*[http://www.usbr.gov/uc/rm/amp/twg/mtgs/16oct18/Attach_07.pdf Fall 2016 HFE Planning]
 
*[http://www.usbr.gov/uc/rm/amp/twg/mtgs/16oct18/Attach_07.pdf Fall 2016 HFE Planning]
 
+
*[[Media:HFE TechTeam Rpt 16oct19.pdf|Technical Team Memo: Final Recommendation to Implement a Fall 2016 High Flow Experiment at Glen Canyon Dam]]
----
+
*[[Media:HFE Leadership Memo 16oct26.pdf|Leadership Team Memo: Approval of Recommendation for Experimental High-Flow release from Glen Canyon Dam, November 7-12, 2016]]
 
+
Dear DOI Glen Canyon Leadership Team,
+
 
+
Please find attached for your consideration the High Flow Experiment (HFE) Technical Team's final conditional recommendation to implement a fall 2016 HFE at Glen Canyon Dam. I am pleased to report the HFE Technical Team's unanimous support of the attached report and recommendation.
+
 
+
In summary, the HFE Technical Team conditionally recommends that an HFE at Glen Canyon Dam be conducted beginning November 7, 2016 with a peak magnitude of approximately 36,000 cubic feet per second for 96 hours, as explained in the attached report, after:
+
# By Friday, October 21, GCMRC and NPS personnel confirm ammonia has provided effective treatment for green sunfish in the upper pond in Glen Canyon, and
+
# DOI commits to prioritizing the development and implementation of non-native species monitoring and mitigation to be in place within the next year.
+
 
+
----
+
  
 
== COMPLIANCE ==
 
== COMPLIANCE ==
 +
*[http://gcdamp.com/index.php?title=The_HFE_Page HFE Protocol]
  
 
== CONCERNS ==
 
== CONCERNS ==
*[[Media:Katrina 2016 HFE final 10-13-16.pdf| Angler's concerns regarding a Fall 2016 High flow experiment]]
+
*[[Media:20171219 GCPBA HFE comments.pdf| Grand Canyon Private Boater's Association (GCPBA) letter requesting '''slower downramp rates''' following the Fall 2016 High flow experiment.]]
*[http://gcdamp.com/index.php?title=Green_Sunfish_Page Re-emergence of green sunfish in the -12 Mile Slough]
+
*[[Media:Katrina 2016 HFE final 10-13-16.pdf| Angler's concerns regarding a Fall 2016 High flow experiment]] on [http://gcdamp.com/index.php?title=FOOD_BASE '''foodbase'''], [http://gcdamp.com/index.php?title=FISHERY '''trout condition''',] and disbursement of [http://gcdamp.com/index.php?title=Green_Sunfish_Page '''green sunfish'''.] Also, noted that a comprehensive written three year review of the first three HFEs has not been provided yet.
*[http://www.usbr.gov/uc/rm/amp/twg/mtgs/16jan26/documents/Attach_05.pdf Increase in brown trout spawning and the increased prevalence of adult brown trout in the Lees Ferry reach since the beginning of the HFE Protocol]
+
*Re-emergence of [http://gcdamp.com/index.php?title=Green_Sunfish_Page '''green sunfish'''] in the -12 Mile Slough.
 
+
*Increase in [http://gcdamp.com/index.php?title=Brown_Trout '''brown trout'''] spawning and the increased prevalence of adult brown trout in the Lees Ferry reach since the beginning of the HFE Protocol.
== SEDIMENT ==
+
  
 
== ADDITIONAL ==
 
== ADDITIONAL ==
Line 75: Line 86:
 
*[http://www.usbr.gov/uc/rm/gcdHFE/2016/2016DownstreamFlowArrivalMap.pdf Downstream Flow Arrival Timing Map]
 
*[http://www.usbr.gov/uc/rm/gcdHFE/2016/2016DownstreamFlowArrivalMap.pdf Downstream Flow Arrival Timing Map]
 
*[http://www.usbr.gov/uc/rm/gcdHFE/2016/2016ReleasePattern.pdf Glen Canyon Dam Possible HFE Release Pattern]
 
*[http://www.usbr.gov/uc/rm/gcdHFE/2016/2016ReleasePattern.pdf Glen Canyon Dam Possible HFE Release Pattern]
 
 
  
  

Latest revision as of 15:38, 2 July 2020

High Flow Experiment- 2016
CRC 121119 0038.JPG

2016 High Flow Experiment Snapshot

  • The 2016 HFE represents the 4th controlled high flow release conducted under the HFE Protocol.
  • A preliminary analysis of these images indicates that sandbar size increased at 55% of sites, remained unchanged and 30% of sites, and decreased at 15% of sites, a response similar to those observed during each of the 2012-2014 HFEs.
  • Before and after images from the November 2016 HFE from each of the 45 sandbar sites monitored with remotely deployed digital cameras are available here.

Sediment Conditions

Fall Accounting Period
  • Paria input (Jul 1 - Nov 6): 844,748
  • Accumulated in Upper Marble Canyon (Jul 1 - Nov 6, lower bound) = 373,000
  • Accumulated in Lower Marble Canyon (Jul 1 - Nov 6, lower bound) = 72,000
  • Available for HFE: 373,000 + 72,000 = 445,000
HFE Transport
  • Paria input (Nov 7 - 12): 1,000
  • Evacuated from Upper Marble Canyon (Nov 7 - 12, lower bound) = -492,000
  • Evacuated from Lower Marble Canyon (Nov 7 - 12, lower bound) = -184,000
  • Left over in Marble Canyon after HFE (Nov 7 - 12): 445,000 + 1,000 - 492,000 - 184,000 = -230,000
Spring Accounting Period
  • Paria input (Dec 1 to Apr 1): 160,000
  • Evacuated from Upper Marble Canyon (Dec 1 to Apr 1, lower bound) = -241,000
  • Evacuated from Lower Marble Canyon (Dec 1 to Apr 1, lower bound) = -81,000
  • Available for spring HFE: -241,000 - 81,000 = -322,000

HFE Details

Schedule & Duration

  • Nov. 7 - 6 a.m. begin upramp to powerplant capacity ( ~21,000 cfs)
  • Nov. 7 - 10:00 a.m. open bypass tubes, reach full bypass at 12:00 p.m.
  • Nov. 11 - 12:00 p.m. end of bypass
  • Nov. 12 - 3:00 a.m. end of HFE
  • Total duration: 5 days & 5 hours (96 hours at peak release)

Ramp Rates

  • Ramp up: 4,000 cfs/hr from 6,500 - 21,000 cfs, then 3,750 cfs/hr to peak (36,000 cfs)
  • Ramp down: 1,875 cfs/hr from 36,000 - 21,000 cfs, then 1,500 cfs/hr to 9,000 cfs

HFE Release Details

  • Maximum total release: 36,000 cfs
  • Powerplant capacity: 21,000 cfs
  • River outlet tubes: 15,000 cfs
  • Hydropower generation units available: 6
  • River outlet tubes: 4

Releases and Lake Elevation

  • Releases will range from 6,500 - 9,000 cfs prior to and after the HFE
  • Lake elevation is projected to decrease by approximately 2.5 feet during the 5-day period
  • Estimated acre feet of water bypassed during HFE: 125 kaf
  • November volume = 745 kaf

Costs

  • Estimated costs to hydropower: $1.4 million
  • Actual costs to hydropower: 1.15 million
  • Direct expenses for removal of concession assets: TBD